RWE
npower, which manages and operates Didcot power station,
has announced it had proposed a new ecological solution
for the disposal of ash created in the electricity
generation process.
The company's new proposal, submitted on 30 January
2006, to Oxfordshire County Council, would avoid the
infill and restoration of the ‘Lake F' gravel extraction
pit in Radley, known locally as Bullfield Lake.
In
June 2005 the company sought approval to fill
Lakes F (Bullfield)
and E (Thrupp) at Radley with pulverised fuel
ash (PFA) which results from burning coal.
RWE
npower has had planning permission since
1982 to fill the former gravel pits at Radley with
PFA, which were regarded as an eyesore when first
created. The older sites, however, have since developed
their own ecology. In response to concerns raised
during the consultation process, RWE npower has submitted
a new application which would guarantee not to fill
Lake F, the more ecologically mature of the two lakes.
Station
manager John Rainford said, “Didcot
Power Station is a vital part of the country's power
generation network. The demand for electricity creates
the need for a 24 hour-a-day, seven-day-a-week option
for disposing of the ash that industry has no use
for. Infill of the old gravel pits has been a good
solution environmentally, avoiding the need to send
hundreds of heavy-laden lorries every day out of Didcot.”
“Our
intial plans, which we maintain are sound, included
a restoration programme; in fact scarce birds, insects
and plants are thriving on previously restored lakes.
However we do recognise that Lake F (Bullfield Lake)
in particular has developed some mature ecology of
interest to many Radley residents.”
“We
have gone back to our engineers and ecologists and
found a different way round. This means we can avoid
using Lake F for infill and we also propose to keep
some public access to the ecologiclly restored areas.”
The
company needs to dispose of 500,000 tonnes of the
non-hazardous ‘pulverised fuel ash' and the new solution
will enable that capacity to be taken by Lake E.
Following
the works at Lake E the plans allow for an extensive
ecological restoration. This would include:
John
Rainford said every effort would be taken
to minimise disruption from the works themselves:
“Before drainage occurs a fish rescue will take
place in consultation with the local authorities.
Temporary fences will be erected before works begin
to protect some areas of trees around Lake E and F.
Meanwhile we will have strict limits on construction
hours and we will not be obstructing public rights
of way,” he said.
The
company said it was looking for an appropriate partner
to manage a nature reserve on the site in the future.
Notes
1.
RWE npower recycles around 50% of its fuel ash to
be used constructively in industry, for instance in
building projects. Unfortunately, although the ash
is not hazardous, it is classified as a waste. This
means extra regulations are attached which can make
it too expensive and time consuming for companies
to take. This also rules out its use in so called
‘grouting' operations, for instance filling in old
mine workings.
2.
RWE npower has opened a new ash processing plant at
Didcot. The £3 million investment will enable
more of the station's pulverised fuel ash (PFA) to
be recycled for use in the building industry. The
equipment has been developed and manufactured by Separation
Technologies Inc (STI) of Boston USA who will operate
the reprocessing plant in partnership with RWE npower.
It is the first of its type to be installed in England
and will be capable of processing 125,000 tonnes of
PFA per year for sale into new markets.
3.
Planning permission has existed since 1982 at the
two lakes in question for the disposal of ash. RWE
npower applied for planning permission for filling
Lake E and F in June 2005 and asked Oxfordshire County
Council for Deferment in the decision of this application
in September so we could address all the concerns
raised during the consultation process. The application
for Lake E only is a new application and in addition
to the application for lake E and F. The two lakes
(E and F) potentially have the capacity to take up
to 600,000 tonnes of ash. The new application for
Lake E only will include engineering to provide the
same overall capacity.
4.
RWE npower has an excellent track record in careful
relocation of protected species. This is something
we take very seriously and we would continue to follow
the best recommended approaches to dealing with any
protected species on the site.