School extension works start

You will see increased activity in Church Road in coming weeks as Ashe Construction, the contractors for the school extension start to create their site access.  Their contract manager explains:

Over the next two to three weeks, we will be forming the temporary entrance, road, and compound area, that will provide access to the rear of the school for the duration of the works.

We will have a “give and take” road plan in place to provide a safe working area for our groundwork contractor to form the new entrance. This will close one lane of the highway with signage in place to give priority to one direction of traffic. We will endeavour to keep the disruption in the road to a minimum.

We are programmed to be on site for 37 weeks and plan to handover the completed works in October 2022.

Map showing access to the school extension building site